Configuring the holiday calendar
The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page.
https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview
Configuring the holiday calendar
With WBS Gantt-Chart, holidays and non-working days are taken into account when creating/modifying plans. Follow these steps to configure non-working days.
- ⇒ Choose Add-ons.
- Select Calendars.
- Select (Default) project Details.
- Click Edit Calendar.
- Edit holiday calendar settings:
- If there are no regular holidays, check Irregular holidays;
- If there are regular holidays, select 1st regular holiday, or 2nd regular holiday, according to the number of non-working days;
- For individual holidays, enter each day under Holiday in the format YYYY-MM-DD;
- Click Update.
You’ve now completed the basic configuration. Next, let’s try managing a project.
More information
If you would like to know about settings not mentioned in this tutorial, please refer to the Administrator Guide for more information.
, multiple selections available,
Related content
Configure working calendar
Configure working calendar
More like this
Configure working calendar
Configure working calendar
More like this
Assign custom calendars to resources
Assign custom calendars to resources
More like this
Show week number
Show week number
More like this
Instruction for Resolving missing Start/Finish Dates on the Gantt Screen (Version 1.2.4-AC)
Instruction for Resolving missing Start/Finish Dates on the Gantt Screen (Version 1.2.4-AC)
More like this
Start Date and Other Gantt-Chart Data Missing in Team Managed Project
Start Date and Other Gantt-Chart Data Missing in Team Managed Project
More like this