Creating a Gantt
In WBS Gantt-Chart, the Gantt is the basic unit you use for managing your project.
A Gantt is similar to a Jira Software board.
Follow these steps to create your Gantt.
Creating a Gantt
Select WBS Gantt-Chart ⇒ Create Gantt.
On the next screen, click Create Gantt button under Create from project or Create from filter.
Enter the Gantt information:
Enter the board name for the Gantt name;
Select the project or filter for which you are using the Gantt.
- Select whether to allow Operation by non-administrators.
Click Create.
The Gantt is displayed once it is successfully created.
Next time, you can display the Gantt you have created by choosing the Gantt’s name from WBS Gantt-Chart or All Gantts.