Creating a Gantt

In WBS Gantt-Chart, the Gantt is the basic unit you use for managing your project.

A Gantt is similar to a Jira Software board.

Follow these steps to create your Gantt.

Creating a Gantt

  1. Select WBS Gantt-ChartCreate Gantt.

  2. Click Create from project under Create Gantt.

  3. Enter the Gantt settings:

    1. Enter the board name for the Gantt name;

    2. Select the project for which you are using the Gantt.

    3. Select whether to allow Operation by non-administrators.
  4. Click Create.

The Gantt is displayed once it is successfully created.

Next time, you can display the Gantt you have created by choosing the Gantt’s name from WBS Gantt-Chart or All Gantts.

Next, we show you how to configure Gantt settings.