The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page. https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview



You are viewing documentation for WBS Gantt-Chart for Jira Server and Data Center. For Cloud, see WBS Gantt-Chart for Jira Cloud.
If you notice that the content is incorrect, please report it here.


Creating a Gantt

In WBS Gantt-Chart, the Gantt is the basic unit you use for managing your project.

A Gantt is similar to a Jira Software board.

Follow these steps to create your Gantt.

Creating a Gantt

  1. Select WBS Gantt-Chart ⇒ Create Gantt.

  2. Click Create from project under Create Gantt.

  3. Enter the Gantt settings:

    1. Enter the board name for the Gantt name;

    2. Select the project for which you are using the Gantt.

    3. Select whether to allow Operation by non-administrators.
  4. Click Create.

The Gantt is displayed once it is successfully created.

Next time, you can display the Gantt you have created by choosing the Gantt’s name from WBS Gantt-Chart or All Gantts.

Next, we show you how to configure Gantt settings.




Unable to render {include} The included page could not be found.