Creating and deleting a dependency
Creating a dependency
Dragging the edge of an issue to the edge of another issue creates a dependency between the two issues.
- Move the cursor on the Gantt bar of a predecessor issue.
- Drag the connector.
- Drop on the connector of the successor issue Gantt bar.
A dependency cannot be created if issues have a parent-child relationship, or if the two issues are identical. Also, if a connector is not displayed, the settings do not allow to create that kind of dependency.
Deleting a dependency
Delete from the contextual menu of the issue.
- Right-click on the issue.
- Delete dependency ... ⇒ Select the dependency you want to delete