The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page. https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview



You are viewing documentation for WBS Gantt-Chart for Jira Server and Data Center. For Cloud, see WBS Gantt-Chart for Jira Cloud.
If you notice that the content is incorrect, please report it here.


Creating and deleting a dependency

On this page:



Creating a dependency

Dragging the edge of an issue to the edge of another issue creates a dependency between the two issues.

  1. Move the cursor on the Gantt bar of a predecessor issue.
  2. Drag the connector.
  3. Drop on the connector of the successor issue Gantt bar.

A dependency cannot be created if issues have a parent-child relationship, or if the two issues are identical. Also, if a connector is not displayed, the settings do not allow to create that kind of dependency.


Deleting a dependency

Delete from the contextual menu of the issue.

  1. Right-click on the issue.
  2. Delete dependency ... ⇒ Select the dependency you want to delete



Unable to render {include} The included page could not be found.